Fee Schedule 2024 Approved
Water Service Rates | ||||
Base rate per month | 2024 | |||
5/8 inch meter | $28.46 | |||
1 inch meter | $50.66 | |||
1 1/2 inch meter | $113.85 | |||
2 inch meter | $202.37 | |||
3 inch meter | $455.39 | |||
Residential & commercial rates | ||||
1,000 to 8,000 | $3.00 | per 1000 gallons | ||
8,001 to 20,000 | $3.46 | per 1000 gallons | ||
20,001 to 35,000 | $5.27 | per 1000 gallons | ||
35,001 to 50,000 | $6.73 | per 1000 gallons | ||
over 50,000 | $8.09 | per 1000 gallons | ||
Late fees and shut offs | ||||
Late fee (after 2 months) | $10.00 | |||
Door hanger (reminder) | $15.00 | |||
Turn on after shut off | $25.00 | $40 second + times/year | ||
Charge for shut offs requested by Cities | $25.00 | $40 second + times/year | ||
Return check fee | $30.00 | |||
Tampering Fee 1st Offense 2nd Offense 3rd Offense – | Legal Action will | be taken | $250 ## $500 ## | plus damages and cost of stolen water |
Copies | $0.20 | per sheet | ||
Faxes (Outgoing) | $1.00 | per sheet | ||
Faxes (Incoming) | $1.20 | per sheet | ||
Deffered Payment Agreement | 1.5% | interest per month | ||
## Legal action may also be taken | ||||
Supply Prices – based on cost at time of purchase. Subject to change* | ||||
Prices may vary based on current market value. | 2024 | |||
MXU Pit Version Single Port for all meters | ||||
Meters | ||||
3/4″ &5/8″ | *all prices are based on cost at time of purchase.* | |||
1″ | ||||
1.5″ | ||||
2″ | ||||
3″ | ||||
4″ | ||||
Repair/ replacement of meter boxes, lids, meter setters and grade rings will be charged at cost at time of purchase plus labor. * | ||||
Fire Hydrants | 2024 | |||
Hydrant – New Installation | $9,400.00 | |||
Hydrant meter rental | per 1000 gallons | $8.09 | ||
Per week | $25.00 | |||
Hydrant repair/replace | cost of parts and labor* | |||
Hydrant meter replacement – based on current market value* | ||||
Hand Valve and Double Check replacement – based on current maket value* | ||||
Subdivisions | ||||
Application Fee | $100.00 | |||
Engineer Review Fee | 1-Lot | $100.00 | ||
Engineer Review Fee | 2-10 Lots | $200 + $100 per lot | ||
Engineer Review Fee | 11+ Lots | $450 + $50 per lot | ||
Inspection Fee | $100.00 | |||
Impact Fee | per lot due before construction of development | $4,809 (District 1) $8,145.67 (District 2) | ||
Labor Prices | ||||
Based on rate at time of service * Subject to change | ||||
*Equipment Hourly Rate | * $80/ hour | |||
*Man Hours | * Subject to rate at time of service |